In this fictional winter fair, the supplier sends the assistant manager a revised marquee drawing with the hire fee unchanged. The setup lead circles the new position. It will take the crew another hour to move everything into place, and the power supplier has priced an extra cable. What should go in the forecast before anyone agrees to revision B?
Follow the change beyond the hire quote
Ticket Tailor’s 3 September 2026 analysis of UK festival budgets describes the cost of putting a site together, drawing on sector data, accounts and published models. The numbers below are Crewbright’s fictional exercise. For a real change, use the agreed rates and scope from the contracts for your event.
Place the two drawings side by side. Revision A is the authorised layout. Revision B moves the marquee further from the power supply. Ask the setup lead for the extra crew-hours and the power supplier what the existing hire covers. Keep both estimates separate from anything already committed.
Cost the knock-on work before approving the move
Four people working one extra hour add four crew-hours. At £45 each, that adds £180 to the forecast. Allow another £90 for the cable and the proposed move adds £270 in total. The marquee hire itself adds £0. Use the same tax basis for every figure in the comparison.

An email arrives from the power supplier. The cable length on revision B is already included in the hire. Everything else stays the same. Before reading on, write down the extra amount you would now show in the forecast and the drawing you would give the crew.
The forecast moves to £180
Remove the £90 allowance for extra cable hire. The four crew-hours still add £180, so the revised forecast is £180 above the approved plan. The supplier has confirmed what the hire covers. The event’s budget holder still has to decide whether to commit the extra labour. Until that decision, the crew work from revision A.
Give the next planner an entry they can use
In the event budget change log, enter “Revision B, marquee move” under change reference. Under proposed change, enter “Four extra crew-hours, £180 forecast. Cable included in existing hire.” Set decision owner to the event budget holder. Under approved version, enter “A. B awaiting approval.”
Hand the two drawings and the entry to the next planner. They should be able to tell the setup lead which drawing to build from and the budget holder how much extra spend is awaiting a decision. When a new revision is approved, enter its reference and the recipients in the log, then brief the affected teams.