How to track an event budget change

An event planner checks costs in a portable site cabin, with the festival stage and a telehandler outside.
An event planner checks costs in a portable site cabin, with the festival stage and a telehandler outside.

A revised event cost arrives after the budget was agreed. Use the change log to separate the forecast from money the budget holder has already authorised.

Use the Event budget change log template to follow the example, or download the individual worksheet.

With £2,400 approved, £1,800 committed and £350 forecast, headroom is £250. A £300 variation takes the forecast £50 over budget. Record the effect and seek the delegated decision before accepting the variation.

Work through the example

Track estimated, committed and actual costs in separate columns. A committed purchase is an expected liability even before an invoice arrives. Compare figures on the same tax basis and record whether delivery and collection are included. Keep contingency visible and require the delegated approval for its use. The approved zone budget is £2,400. Confirmed commitments total £1,800 and remaining expected costs are £350 on the same basis. Forecast headroom is £250. A supplier requests an extra £300. Escalate the £50 forecast overrun with options before accepting the change.

Free printable record

Copy these fields into your shift notes, or print this page and complete them with your supervisor.

Change reference ____________________

existing commitments ____________________

forecast remaining spend ____________________

proposed change ____________________

impact on access and timing ____________________

decision owner ____________________

approved version ____________________

recipients ____________________

Related training

Event Planning for Assistant Managers

A supplier now includes an item previously costed at £40, while an extra two crew-hours at £20 each still apply. What is the revised forecast increase?

Compare your decision

The extra labour adds £40. Remove the separate £40 supplier allowance and record the revised forecast, the supplier confirmation and who can approve the change.